NHS BARNSLEY HOSPITAL

PROJECT UPDATE  |  MAY 2021

PROGRESS REPORT

BDGH Phase 3 is making good progress, The redundant children assessment ward is presently being remodelled to extend the facilities inside the existing emergency department at Barnsley Hospital.

The Mechanical services installation is well under way and on program, CPS have completed all their mechanical first fix including the installation of 70 metres of ventilation Ductwork, 105meters of copper pipe, and all medical gas piped services.

THE STATS

80m

Medical Gases Pipework

70m

Duct Work

120m

Copper Pipework

PROJECT GALLERY

Click view larger image

NHS BARNSLEY HOSPITAL

PROJECT UPDATE  |  JAN 2021

Barnsley Hospital is investing £3.5m into this dedicated, co-located Children’s Emergency Department and a brand new purpose-built Children’s Assessment Unit.

Over the last few weeks, progress on site has continued to move on at pace. The roof finishes are 100% complete, with a big thank you to Malden Roofing for a fantastic and quality job.

Our mechanical and electrical subcontractors have commenced their installations on the roof and plant room levels. Complete Pipework Services have connected the ductwork and other services to the new air handling unit.
The specialist, external envelope contractor, OSG, are processing well with the rain screen cladding and you can see the finished panels, colours and shapes that provide a distinctive and individual identity to the new facility. Our plans, weather permitting will see the cladding completed before the Christmas break allowing the external works to commence immediately after.

Inside the building, now completely plastered and painted which has made a massive difference, you can now see the spaces starting to take shape. In a number of rooms, preparations have begun in readiness for applying the new vinyl flooring.

Off-site, the integrated plumbing systems (IPS) have gone into manufacture with a number of these already delivered and installed. Along with the new Mediplan bed head modules. The internal doors are nearing the end of manufacture and will be soon making their way to site.

Also progressed on-site:


  • Internally, mechanical and electrical works have pushed on considerably
  • Second fix works, wiring for sockets and lights is nearing completion
  • The new data wiring/installation is completed
  • CPS is nearing completion on installing the new ventilation system and will be moving on to completing the heating system
  • Fire stopping has started to all the penetrations through the fire rated walls
  • External doors have now been fitted to the building
  • The existing stair core has been freshly rendered and had a new coat of paint
  • Works to bring ventilation into the existing ED department are underway
  • All breaking through into the existing building is now complete
  • Preparation works for the new suspended celling are progressing

MEET THE TEAM:

Ricky Burton
Mechanical Foreman

How long have you been a part of Complete Pipework Services?
I have worked for CPS for 6 years.

What do you think about the project?
I think this is a fantastic and exciting project that I'm very proud to be part of. It will be a great facility for the people of Barnsley.

Where are you from?
Born and raised in Barnsley

What do you like to do outside of work?
I enjoy walking, playing a bit of golf and socialising with friends.

PROJECT GALLERY

Click view larger image